Meter Installation in 4838 Reactor Controller 1. Unplug the power cord of the 4838 controller. Remove the (2) screws located on the top corners
- 10 - PDM Installation This page left blank intentionally.
- 11 - PDM Installation This page left blank intentionally.
Revision 05/15/09 Parr Instrument Company 211 53rd Street • Moline, Illinois 61265 USA 1-309-762-7716 • 1-800-872-7720 • Fax: 1-309-762-9453 E-mai
- 2 - PDM Installation Meter installation in 4838 Reactor Controller (continued) Meter Installation Diagram 4. Mount the 2068E power supply, o
- 3 - PDM Installation Wiring installation in the 4838 Reactor Controller 1. If applicable, remove the black hole plug on the back of the contro
- 4 - PDM Installation Wiring installation in the 4838 Reactor Controller (continued) 5. Find the loose 3-pin edge connector, with yellow and w
- 5 - PDM Installation Wiring installation in 4838 Reactor Controller (continued) 8. Find the orange wire #8, with both ends stripped, and attac
- 6 - PDM Installation Final Steps Close the controller and replace the two screws on the back panel. Plug the 4838 controller back in, and turn
- 7 - PDM Installation Wiring Schematic
- 8 - PDM Installation Pressure Module Defaults Keys command: 1. Press “SET” to select 2. Press return key move to next operation mode 3. Up/
- 9 - PDM Installation Pressure Module Defaults (continued) Press and hold down “SET” for 5-sec Operation Mode Select type/value Comment InPt